Planning and Designing a New Home for our Family in Houghton, Stockbridge

  • Facebook
  • LinkedIn
  • Twitter
  • Instagram

Author: Dianthus

We’re a happy, hippy family with four lovely children. We’re embarking on an exciting journey of building an eco home that would give us our forever home. One of our children is disabled, therefore, we need to design and build something that has accessibility designed in for him and for the future. We also have a baby and toddler.
Construction Programme Demolition and Groundworks Substructure

Week 20: Preparation for Basement Floor and Pile Cap

Posted on December 9, 2019 by Dianthus
Reading time 1 minute
Construction Programme Demolition and Groundworks Piling Substructure

Week 19: Sika Waterproof Membrane

Posted on November 22, 2019 by Dianthus
Reading time less than 1 minute
Construction Programme Demolition and Groundworks Piling Substructure

Week 18: Drainage and Ducting of the Basement

Posted on November 18, 2019 by Dianthus
Reading time 1 minute
Construction Programme Demolition and Groundworks Substructure

Week 17: Excavating the Spoil from within the Retaining Wall

Posted on November 6, 2019 by Dianthus
Reading time 2 minutes
Demolition and Groundworks Piling Substructure

Week 16-Propping the Capping Beams with Steel Re-Inforcement

Posted on October 31, 2019 by Dianthus
Reading time 2 minutes
Architecture Design Detailed Design Planning Pre-Application

Architecture Design Themes and Considerations

Posted on October 23, 2019 by Dianthus
Reading time 14 minutes
Construction Programme Piling Substructure

Week 15-Substructure-Preparing the Steel Reinforcement for Pouring the Capping Beam

Posted on October 21, 2019 by Dianthus
Reading time 3 minutes
Construction Programme Piling Substructure

Week 12-Substructure-Preparing the ground for Pouring Capping Beam

Posted on October 5, 2019 by Dianthus
Reading time 1 minute
Construction Programme Piling Substructure

Substructure- Preparing to Pour Capping Beam for Basement Construction

Posted on October 1, 2019 by Dianthus
Reading time 2 minutes

Posts navigation

Older posts
Newer posts

Categories

  • Construction Programme (43)
  • Substructure (19)
  • Superstructure (18)
  • Piling (16)
  • Demolition and Groundworks (15)

Tags

  • Dianthus (11)
  • Accessibility (2)
  • Living (2)
  • The Journey Begins (2)
  • Wheelchair (2)

Year

  • 2024 (1)
  • 2023 (5)
  • 2021 (17)
  • 2020 (20)
  • 2019 (28)

Dianthus

Dianthus Logo

Website Powered by WordPress.com.

  • Facebook
  • LinkedIn
  • Twitter
  • Instagram
Dianthus
Website Powered by WordPress.com.
Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Subscribe Subscribed
    • Dianthus
    • Already have a WordPress.com account? Log in now.
    • Dianthus
    • Subscribe Subscribed
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...